Case purpose
Sometimes "the way we do things around here" has to be challenged firmly
and decisively. This is a case study that shows two business leaders stepping
up to a crisis and managing to achieve the outcomes they wanted to.
Case Description
Background
BAA needed a fast passenger link to central London from Heathrow, to cut
journey times especially for business passengers. They chose to build a
fast rail link into Paddington but not to let it be integrated with the
rail network and to run it privately. The main construction contract, including
building the tunnels beneath the airport was let to Balfour Beatty.
Traditional construction industry organisation is to have teams both
sides of each major contract making sure that the terms of the contract
are complied with. So the client has a team of people watching the main
contractor do their job, and there is man-to-man marking in project meetings.
As Sir John Egan, then chairman at BAA, tells the story, the crucial
engineering concern was the airport tunnels. If the airport was disrupted
by problems with the tunnels, the losses to BAA could easily outstrip the
entire future value of the rail link.
The organisational issue
BAA had chosen Balfour Beatty as the best possible tunnelling contractor
as they had just completed the channel tunnel. BAA considered that they
did not understand tunnelling techniques well enough to challenge Balfour
Beatty on their performance.
The key measure in the contract was the subsidence of the ground surface
due to tunnelling underneath. This was supposed to be an indicator that
problems might be developing. Above a certain threshold, Balfour Beatty
were supposed to stop tunnelling and take remedial action. This would incur
time penalties and extras costs.
The danger signs
For several weeks in succession the subsidence figures reported by Balfour
Beatty were right at the threshold limit. Further, there were reports by
workers in the tunnel that subsidence was excessive. None of this led to
remedial action and BAA did not ask for the situation to be reviewed, despite
the normally fierce challenges about performance.
One night while the tunnel was empty, it collapsed, leaving huge hole
in the surface of the airport. By sheer chance the hole did not disrupt
airport operations beyond the initial safety checks.
A crossroads
Normal practice in such cases would be to immediately sue the contractor
for damages to operations and to the project. However, Sir John Egan decided
to put the project first: there was no way the rail link would get built
on time if there was a legal battle, and the revenues from the link were
more important to BAA than the damages.
A crisis meeting was held with Balfour Beatty with the following main
agreements:
-
The main aim was to get the link built on time and to cost.
-
The only way to change the cost and time profile of the project was to
change the culture.
-
The design would be changed to use the site of the collapse as a station.
The new culture
The size of the project team would be slashed by eliminating man-to-man
marking altogether. The client and contractor would work together as partners
and a team of consultants was hired to help them do so. Any issue that
came up between client and contractor that could not be resolved by the
team was guaranteed to be sorted between the company chairmen.
The programme went ahead on that basis after a delay of more than six
months while the Health and Safety Executive (HSE) investigated the tunnelling
method being used to see if it was safe to use. The project was completed
on time and went into service. After the project was finished there was
some legal argumentation about the status of the contracts that had been
abandoned mid-project.
Leadership outcomes
The judgment Sir John Egan made was this. If the existing culture of close
marking bought in practice no protection from the key risk he had identified,
then it was not worth having. If it was not worth having, its large cost
had no justification and the entire system of checking and cross checking
other people’s work should be done away with, in favour of the team taking
joint responsibility for its actions.
In taking that decision, the received wisdom and practice of the entire
industry sector was overturned. One reason Egan was able to do that was
that he came from a different sector, from manufacturing, another reason
was the dominant position of BAA in the industry and a third was political
support.
Despite the excellent performance of the project under the new culture
there has been no general move towards copying the style in order to improve
performance elsewhere in construction.
Questions about leadership
What risks did the company chairmen take by taking the decisions they did?
What risks to themselves? What risks to their companies?
Given the traditions of the industry would you emphasise the leadership
shown after the crisis or the lack of leadership before the crisis?
How did the crisis change the nature of leadership and the demands for
leadership?
Source
Prepared by Aidan Ward, October 2001. Revised October 2002.
 |
 |
[top]
[student page]
[contact us] |
This page last updated on October 15th, 2002
Copyright © 2002 Veryard Projects Ltd & Antelope
Projects Ltd
http://www.veryard.com/orgmgt/caseheathrow.htm
|